Exam Overview
| Exam Code | PRMP |
| Exam Name | Project Risk Management Professional |
| Vendor | AACE International |
| Total Questions | 68 |
| Last Updated | 26-Oct, 2026 |
Why CertsPoint?
- Latest & Verified Questions
- Detailed Explanations
- Regular Updates
- Full-Length Practice Tests
- Boost Your Exam Confidence
PDF Study Materials
Downloadable guides and resources
Practice Tests
Full-length tests with real exam experience
Progress Tracking
Monitor your performance and improvement
Study Anywhere
Access on desktop, tablet, and mobile
Secure Payment
Privacy Protected
Money Back Guarantee
Free PRMP Practice Questions
Explore 5 free practice questions for the AACE International PRMP exam and review the answers and explanations to support your preparation.
-
Question 1
Single answerA project manager wants to rank risks quickly using probability and impact before selecting risks for detailed quantitative analysis. Which process should be performed?
-
Option A:Correct
Contract closeout
-
Option B:Correct
Monte Carlo simulation only
-
Option C:Correct
Qualitative risk analysis
-
Option D:Correct
Final account reconciliation
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: C
Explanation
Qualitative risk analysis prioritizes risks using probability, impact, urgency, and other ranking factors. It is
normally performed before quantitative analysis because it helps determine which risks deserve more
detailed modeling. The result may include risk rankings, risk owners, and risks requiring immediate
response planning. -
-
Question 2
Single answerA project has an Earned Value of $360,000 and an Actual Cost of $450,000. What is the Cost
Performance Index?-
Option A:Correct
0.80
-
Option B:Correct
1.25
-
Option C:Correct
0.20
-
Option D:Correct
1.80
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
Explanation
Cost Performance Index is calculated as CPI = EV ÷ AC. Here, CPI = $360,000 ÷ $450,000 = 0.80. A CPI below 1.0 means the project is over budget because the value earned is less than the cost spent. CPI is commonly used to identify cost performance risk.
-
-
Question 3
Single answerA project team performs risk reassessment during execution. What is the main purpose?
-
Option A:Correct
To eliminate the need for project controls
-
Option B:Correct
To close all risks automatically
-
Option C:Correct
To replace the approved baseline every week
-
Option D:Correct
To identify new risks and update existing risk information
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: D
Explanation
Risk reassessment reviews existing risks, identifies new risks, updates probability and impact, checks response effectiveness, and closes risks that are no longer relevant. Risk management is continuous because project conditions change over time. Regular reassessment improves project control and decision making.
-
-
Question 4
Single answerA risk analyst estimates a cost item as optimistic $80,000, most likely $100,000, and pessimistic $150,000. Using triangular distribution, what is the expected value?
-
Option A:Correct
$100,000
-
Option B:Correct
$110,000
-
Option C:Correct
$150,000
-
Option D:Correct
$330,000
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: B
Explanation
For a triangular distribution, expected value is calculated as (Optimistic + Most Likely + Pessimistic) ÷ 3. Here, ($80,000 + $100,000 + $150,000) ÷ 3 = $330,000 ÷ 3 = $110,000. This method gives equal consideration to all three estimates.
-
-
Question 5
Single answerA project has a most likely activity duration of 20 days, optimistic duration of 14 days, and pessimistic duration of 32 days. What is the PERT expected duration?
-
Option A:Correct
20 days
-
Option B:Correct
22 days
-
Option C:Correct
21 days
-
Option D:Correct
24 days
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: C
Explanation
PERT expected duration = (O + 4M + P) ÷ 6. Here, (14 + 4×20 + 32) ÷ 6 = (14 + 80 + 32) ÷ 6 = 126 ÷ 6 = 21 days. PERT is useful when duration uncertainty exists and three-point estimates are available.
-