| Exam Code | AgilePM-Practitioner |
| Exam Name | APMG-International Agile Project Management (AgilePM) Practitioner |
| Vendor | APMG-International |
| Total Questions | 134 |
| Last Updated | 26-Oct, 2026 |
- Latest & Verified Questions
- Detailed Explanations
- Regular Updates
- Full-Length Practice Tests
- Boost Your Exam Confidence
PDF Study Materials
Downloadable guides and resources
Practice Tests
Full-length tests with real exam experience
Progress Tracking
Monitor your performance and improvement
Study Anywhere
Access on desktop, tablet, and mobile
Free AgilePM-Practitioner Practice Questions
Explore 10 free practice questions for the APMG-International AgilePM-Practitioner exam and review the answers and explanations to support your preparation.
-
Question 1
Multiple answersWhich 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
-
Option A:Correct
Details of which areas will require seeding in order to become lawn, and which are to become planted borders, should be captured.
-
Option B:Correct
The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.
-
Option C:Correct
The scope of the project should be agreed before moving into the Foundations phase.
-
Option D:Correct
The responsibility for setting the priority of each of the requirements identified should be assigned to the Project Manager.
-
Option E:Correct
Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: B, E
Explanation
In the context of Agile Project Management when developing the Prioritised Requirements List during Feasibility, the two statements that align with Agile principles are: B . The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements. E. Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements. Here's the rationale: • B: In Agile, requirements are often categorized by priority such as "Must Have", "Should Have", "Could Have", and "Won't Have for now" (the MoSCoW method). The re-laying of the driveway and a landscaping solution are essential for the project's success and thus should be classified as "Must Have". • E: Regulatory requirements are non-negotiable constraints that the project must adhere to. These should always be prioritized in the requirements list to ensure compliance and to avoid legal issues, making them "Must Have" items as well.
-
-
Question 2
Multiple answersUsing the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
-
Option A:Correct
Paper-based drawings are to be used for each option being considered for the building and gardens.
-
Option B:Correct
The SAD must include a physically-built miniature model of the Hoy Hall building.
-
Option C:Correct
The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.
-
Option D:Correct
The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.
-
Option E:Correct
The SAD should contain high-level costs for all elements of each solution option.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A, C
Explanation
In the context of Agile Project Management when developing the Solution Architecture Definition (SAD), the two statements that are appropriate are: A . Paper-based drawings are to be used for each option being considered for the building and gardens. C . The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution. Here's the rationale: • A: Agile methodologies support the use of simple and understandable tools that can quickly convey ideas and be easily changed. Paper-based drawings align with this by providing a flexible and adaptable way to represent different options, which can be rapidly modified in response to feedback. • C: It is important for the Marketing Director, who understands the market and customer needs, to request clarification on complex elements to ensure that the proposed solutions are feasible and aligned with customer expectations. This contributes to creating a solution that is viable both technically and from a business perspective.
-
-
Question 3
Multiple answersUsing the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when developing the Delivery Plan?
-
Option A:Correct
The Project Manager should include any known constraints associated with planning permission.
-
Option B:Correct
The Project Manager should NOT need to identify any risks this early in the project.
-
Option C:Correct
The approach to the project should be based on the Project Approach Questionnaire responses.
-
Option D:Correct
The Earth Excavations' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.
-
Option E:Correct
The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A, E
Explanation
In the context of Agile Project Management, when developing the Delivery Plan during the Feasibility phase, the two statements that best align with Agile principles are: A . The Project Manager should include any known constraints associated with planning permission. E . The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan. Here's the rationale: • A: Recognizing and accounting for known constraints such as planning permission is a key aspect of Agile. It allows for better adaptability and planning around these constraints. Including them early in the Delivery Plan helps ensure that they are considered throughout the project. • E: Agile emphasizes cross-functional collaboration and stakeholder engagement. The Marketing Director would provide valuable insights into customer needs and market conditions, which are crucial for a successful delivery plan.
-
-
Question 4
Multiple answersUsing the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
-
Option A:Correct
The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.
-
Option B:Correct
Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed.
-
Option C:Correct
During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
-
Option D:Correct
The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.
-
Option E:Correct
The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: B, C
Explanation
In applying Agile Project Management to the creation of an Outline Business Case in support of the Feasibility Assessment, the following two statements are most appropriate: B . Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed. Agile approaches favor providing just enough detail to make informed decisions without going into unnecessary depth at early stages. This allows for flexibility and adaptation as more information becomes available. C . During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
-
-
Question 5
Multiple answersUsingtheProjectScenario and the additional information provided for thisquestionintheScenario Booklet, answer the following questions about Feasibility. Remembertolimityour answers to the number of selections requested in each question. Which2statementsdescribe the appropriate application of Agile Project Managementwhendeveloping the Feasibility Assessment?
-
Option A:Correct
ThenewProjectManager should NOT be involved in finalising the FeasibilityAssessment.
-
Option B:Correct
TheArchitectureAngels' Finance Director should approve the final BusinessCaseaspartof the Feasibility Assessment.
-
Option C:Correct
TheEarthExcavations' Head Gardener should contribute to the outline solutionsconsideredfor the gardens.
-
Option D:Correct
Thedifferentoptions should be presented to the 'Hoy for Hoy Hall' Action Groupfortheirfeedback before the chosen outline solution is finalised.
-
Option E:Correct
TheTimberTigers'Site Manager should be the sole approver of the finalisedFeasibilityAssessment before development commences.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: B, D
Explanation
InAgileProjectManagement, it's important to involve key stakeholders and to ensure that there's a collaborativeapproach to project decisions. Considering the Agile principles and the given scenario, theappropriateapplication of Agile to the Feasibility Assessment would likely involve the following statements: B.TheArchitectureAngels' Finance Director should approve the final Business Case as part of the FeasibilityAssessment. In Agile, it's crucial to ensure that the business aspect of any project aligns withthefinancialfeasibility. The Finance Director's approval would be significant in validating the economicviabilityofthe project.
-
-
Question 6
Single answerAnswer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
-
Option A:Correct
Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.
-
Option B:Correct
Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.
-
Option C:Correct
No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.
-
Option D:Correct
No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders'
expectations.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
-
-
Question 7
Single answerHow should the Project Manager assist the plumbers to deliver the plumbing?-
Option A:Correct
Split the entire Solution Development Team into smaller teams covering specific locations of the house.
-
Option B:Correct
Decide on the location of the radiators on behalf of Architecture Angels.
-
Option C:Correct
Establish an inter-team competition to see which team can complete first.
-
Option D:Correct
Approve each Timebox before work continues in the next.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
-
-
Question 8
Single answerHow should the Project Manager encourage the contractors to turn up on time?
-
Option A: Place a penalty clause on all contractors for late arrival.Correct
-
Option B:Correct
Appoint Team Leaders to each of the electrical and plumbing teams.
-
Option C:Correct
Encourage open and honest communication to re-establish an environment of trust.
-
Option D:Correct
Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: C
-
-
Question 9
Single answerThe building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
-
Option A:Correct
Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.
-
Option B:Correct
Hold a separate Daily Stand-up meeting for contractors only.
-
Option C:Correct
Provide a detailed plan of activity for each contractor team
-
Option D:Correct
Schedule the electrical and plumbing teams so that they work on different Timeboxes
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: C
-
-
Question 10
Multiple answersWhich 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
-
Option A:Correct
Accustomed to bringing in contract staff for short periods of time.
-
Option B:Correct
Accustomed to bringing in contract staff for short periods of time.
-
Option C:Correct
Is able to represent the team in all daily meetings
-
Option D:Correct
An experienced builder who is good at turning a brief into a practical design.
-
Option E:Correct
Is empowered by Timber Tigers' management to make decisions on the building work.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: B, D
-