Preparing for the AgilePM-Foundation exam is simple with CertsPoint. We offer easy-to-understand study materials that help you learn the most important exam topics. You can study using our PDF questions, practice online with a real exam-style test, or use the desktop practice software. Choose the study method that works best for you and prepare at your own pace.

At CertsPoint, we keep our AgilePM-Foundation practice questions up to date. Whenever the exam syllabus or objectives change, we update our study materials so you always learn the latest topics. This helps you save time, avoid outdated content, and feel more confident when you take your exam.

Download Exam View Entire Exam
Page: 2 / 2
Question #6 (Topic: demo questions)

How does DSDM differ from most other Agile approaches?

A.

It focuses on the entire project lifecycle


B.

It focuses on the development of products


C.

It focuses on the delivery of products


D.

It focuses on the collaborative working of teams

Correct Answer: A
Explanation:

DSDM differs from most other Agile approaches because it focuses on the entire project lifecycle 4 5 6 . This includes pre-project, feasibility, foundations, development, and deployment phases, ensuring a comprehensive approach to project management.

Question #7 (Topic: demo questions)

Identify the missing words in the following sentence.

AgilePM planning concepts help keep [?] without excessive bureaucracy.

A.

Scrum work progressing


B.

projects on track


C.

Backlog items arranged


D.

commitments in place

Correct Answer: B
Explanation:

gilePM emphasizes lightweight but effective planning that maintains control without bureaucracy . Core planning concepts include timeboxing (fixed-duration delivery windows), MoSCoW prioritization (flexing scope to protect time/cost/quality), incremental and iterative delivery (frequent demonstrations and review), and rolling-wave planning (planning at multiple horizons). Together these techniques ensure transparency, predictable cadence, and early value while avoiding heavyweight documentation or rigid stage gates. Plans are living forecasts refined through continuous feedback and empirical evidence from delivered increments. Governance focuses on outcomes and fitness for purpose rather than exhaustive upfront detail. This is why the guidance often summarizes that AgilePM planning “keeps projects on track ,” enabling teams to respond to change, surface risks early, and align stakeholders around real progress. Options A, C, and D capture fragments of agile practice, but they understate the project-level intent. The correct completion is “projects on track.”

Question #8 (Topic: demo questions)

How is contingency typically managed in a DSDM project?

A.

Not needed in a DSDM project.


B.

Allowed adding a percentage to the high-level estimates.


C.

Managed by varying the features to be delivered.


D.

Managed by varying time and cost

Correct Answer: C
Explanation:

In a DSDM project, contingency is typically managed by varying the features to be delivered 6 . This approach aligns with the DSDM principle of delivering the most critical work first and using the MoSCoW prioritization to adjust the scope of delivery as needed.

Question #9 (Topic: demo questions)

Which of the common Agile concepts, behaviors, and techniques delivers a version of a product with just enough features to be usable by early customers who can then provide feedback for future product development?

A.

Minimum viable product.


B.

Full transparency.


C.

Self-organized teams.


D.

Empowerment.

Correct Answer: A
Explanation:

    Minimum Viable Product (MVP) : An MVP allows early customers to use a product and provide valuable feedback, which is then incorporated into subsequent iterations. This is central to Agile practices, emphasizing incremental delivery and responsiveness to user needs.

    Other Options :

      B : Full transparency relates to visibility into processes and progress, not product development.

      C and D : These refer to team dynamics, not product delivery.

Key AgilePM Concepts Referenced :

    Incremental Delivery : AgilePM Handbook, Chapter 3, Section 3.7.

Question #10 (Topic: demo questions)

Which of the following statements are true?

    The ' change curve ' describes a normal human reaction to change.

    The ' change curve ' only applies to changes that are perceived as negative.

A.

Only 1 is true.


B.

Only 2 is true.


C.

Both 1 and 2 are true.


D.

Neither 1 nor 2 is true.

Correct Answer: A
Explanation:

    Statement 1 : Correct . The change curve describes typical emotional responses to change, including denial, resistance, exploration, and commitment.

    Statement 2 : Incorrect . The change curve applies to both positive and negative changes, as it reflects the adjustment process regardless of the perceived nature of the change.

Key AgilePM Concepts Referenced :

    Emotional Responses to Change : AgilePM Handbook, Chapter 6, Section 6.3.

Download Exam