CertsPoint
See all results for ""
Exams About Us
Sign In Get Started
Exam Overview
Exam Code PgMP
Exam Name Program Management Professional (PMI-PgMP)
Vendor PMI
Total Questions 452
Last Updated 26-Oct, 2026
Why CertsPoint?
  • Latest & Verified Questions
  • Detailed Explanations
  • Regular Updates
  • Full-Length Practice Tests
  • Boost Your Exam Confidence

PDF Study Materials

Downloadable guides and resources

Practice Tests

Full-length tests with real exam experience

Progress Tracking

Monitor your performance and improvement

Study Anywhere

Access on desktop, tablet, and mobile

Excellent
4.6 (398 Up Votes)
Secure Payment Privacy Protected Money Back Guarantee

Free PgMP Practice Questions

Explore 5 free practice questions for the PMI PgMP exam and review the answers and explanations to support your preparation.

  1. Question 1

    Single answer

    The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.

    Where is this expectation documented?

    • Option A:

      Program quality standards

      Correct
    • Option B:

      Customer management plan

      Correct
    • Option C:

      Benefits management plan

      Correct
    • Option D:

      Benefits sustainment plan

      Correct
    Show Answer & Explanation Hide Answer & Explanation

    Correct Answer: A

  2. Question 2

    Single answer

    After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.

    Based on this information, the program manager determines which of the following?

    • Option A:

      The schedule is US$30,000 under budget

      Correct
    • Option B:

      The cost is US$20,000 under budget

      Correct
    • Option C:

      The schedule is US$10,000 over budget

      Correct
    • Option D:

      The cost is US$20,000 over budget

      Correct
    Show Answer & Explanation Hide Answer & Explanation

    Correct Answer: D

  3. Question 3

    Single answer

    A software company ' s program manager is conducting closing procedures for a program. At the last steering

    committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

    • Option A:

      Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program ' s status.

      Correct
    • Option B:

      Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.

      Correct
    • Option C:

      Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.

      Correct
    • Option D:

      Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization.

      Correct
    Show Answer & Explanation Hide Answer & Explanation

    Correct Answer: A

  4. Question 4

    Single answer

    A program with six projects has been running for three years. The company’s procurement and contracts department has compiled a qualified seller list.

    The program manager determines that one of the projects must be outsourced.

    The program manager will use the qualified seller list to do which of the following?

    • Option A:

      Plan a proposal evaluation system

      Correct
    • Option B:

      Prepare the program procurement management plan

      Correct
    • Option C:

      Perform the required program budget updates


      Correct
    • Option D:

      Issue requests for proposals

      Correct
    Show Answer & Explanation Hide Answer & Explanation

    Correct Answer: D

  5. Question 5

    Single answer

    Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

    • Option A:

      Decompose the program work based upon available resources

      Correct
    • Option B:

      Decompose the program to the work package level

      Correct
    • Option C:

      Decompose the program to the architecture baseline level

      Correct
    • Option D:

      Decompose the program at a level sufficient to achieve control

      Correct
    Show Answer & Explanation Hide Answer & Explanation

    Correct Answer: A