| Exam Code | PgMP |
| Exam Name | Program Management Professional (PMI-PgMP) |
| Vendor | PMI |
| Total Questions | 452 |
| Last Updated | 26-Oct, 2026 |
- Latest & Verified Questions
- Detailed Explanations
- Regular Updates
- Full-Length Practice Tests
- Boost Your Exam Confidence
PDF Study Materials
Downloadable guides and resources
Practice Tests
Full-length tests with real exam experience
Progress Tracking
Monitor your performance and improvement
Study Anywhere
Access on desktop, tablet, and mobile
Free PgMP Practice Questions
Explore 5 free practice questions for the PMI PgMP exam and review the answers and explanations to support your preparation.
-
Question 1
Single answerThe chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.
Where is this expectation documented?
-
Option A:Correct
Program quality standards
-
Option B:Correct
Customer management plan
-
Option C:Correct
Benefits management plan
-
Option D:Correct
Benefits sustainment plan
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
-
-
Question 2
Single answerAfter taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.
Based on this information, the program manager determines which of the following?
-
Option A:Correct
The schedule is US$30,000 under budget
-
Option B:Correct
The cost is US$20,000 under budget
-
Option C:Correct
The schedule is US$10,000 over budget
-
Option D:Correct
The cost is US$20,000 over budget
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: D
-
-
Question 3
Single answerA software company ' s program manager is conducting closing procedures for a program. At the last steering
committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?
-
Option A:Correct
Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program ' s status.
-
Option B:Correct
Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.
-
Option C:Correct
Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.
-
Option D:Correct
Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization.
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
-
-
Question 4
Single answerA program with six projects has been running for three years. The company’s procurement and contracts department has compiled a qualified seller list.
The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?
-
Option A:Correct
Plan a proposal evaluation system
-
Option B:Correct
Prepare the program procurement management plan
-
Option C:Correct
Perform the required program budget updates
-
Option D:Correct
Issue requests for proposals
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: D
-
-
Question 5
Single answerWhich of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
-
Option A:Correct
Decompose the program work based upon available resources
-
Option B:Correct
Decompose the program to the work package level
-
Option C:Correct
Decompose the program to the architecture baseline level
-
Option D:Correct
Decompose the program at a level sufficient to achieve control
Show Answer & Explanation Hide Answer & Explanation
Correct Answer: A
-